The City is making improvements to 125th and East French Lake Road.  The project involves resurfacing the existing roadway without any changes to its current alignment or width.  The road will remain open to traffic throughout the duration of the work; however, please expect delays within the construction zone.  Traffic will be managed by flaggers to ensure safety and maintain traffic flow.

The anticipated timeline is as follows:

Preliminary Work:                                       October 1st and 2nd
Culvert Repair & Replacement:                  October 6th through 10th
Concrete Curb & Gutter:                             October 8th through 10th
Remove Bituminous Pavement:                 October 15th through 17th
Pave Bituminous:                                        October 20th through 22nd
Street Striping:                                            October 27th through 28th

If you have any questions, please contact Nick Findley at (952) 334-0653 or Martin Farrell at (612) 751-8847