As of September 09, 2019, the utility work along Rush Creek Parkway is complete. Construction of the permanent roadway is underway, with roughly one-third of it being nearly ready for paving, the remaining two-thirds being prepared for the placement of base materials. The contractor’s estimated schedule includes paving the week of September 23rd; it is after paving that the roadway can be reopened to traffic. As always, the schedule is subject to weather conditions and may need to be adjusted as the work continues.