Park Improvement Projects current timeline.  These are the most accurate dates as of 08/31/2020, but are subject to change due to weather or unforeseen circumstances.

Stephen Park

  • 08/28/2020 – Pergola Manufacture and delivery to site.
  • 09/02/2020 – Pergola Installation
  • 09/04/2020 – Natural stone block seating delivered
  • 09/18/2020 – Concrete paver installation completion
  • 09/22/2020 – Fine grade landscaping completion
  • 09/25/2020 – Electrical installation completion
  • 09/29/2020 – Landscaping completion
  • 09/30/2020 – Install Railings

River Hills Park

  • 09/01/2020 – Concrete salb for shelter completion
  • 09/02/2020 – Fine grade trail completion
  • 09/03/2020 – Playground concrete curbing completion
  • 09/04/2020 – General excavation work to be completed
  • 09/22/2020  -Trail paving completion
  • 09/11/2020 – Shelters manufactured and delivered to site
  • 09/14/2020 – Fine grade for landscaping completion
  • 09/16/2020 – Paint pickle ball courts
  • 09/16/2020 – Concrete Paving – Shelter Slab
  • 09/22/2020 – Park furniture installation
  • 09/21/2020 – Install shelter (16 x 24) by pickle ball courts completion
  • 09/23/2020 – Granite pathways around pollinator garden completion
  • 09/23/2020 – Concrete paving around pollinator garden completion
  • 09/24/2020 – Site furniture installation completion
  • 09/24/2020 – Pollinator garden shelter installation completion
  • 09/28/2020 – Install shelter (16 x 16)
  • 10/01/2020 – Landscaping completion

Sundance Woods Park

  • 09/03/2020 – Paint basketball court completion
  • 09/04/2020 – General excavation work completion
  • 09/15/2020 – Pave trail completion
  • 09/10/2020 – Fine grading for landscaping completion
  • 09/11/2020 – Shelter manufactured and delivery to site
  • 09/21/2020 – Landscaping installation completion
  • 10/01/2020 – Shelter installation completion

We have a project completion deadline of 10/30/2020.