Construction Update 09/29/2022:

  • We are working on the 300 series manholes and piping this week.  Should finish with that on 10-3-22.
  • We will start on the 400 series manholes and pipe on Tuesday 10-4-22 and should finish them on 10-11-22.
  • We will finish the 20” watermain on 10-12 thru 10-13.
  • We will start street excavation/sand and rock import on 10-10-22.  We anticipate this taking through 10-28-22.
  • We are hoping for curb starting 10-31-22 ending 11-4-22 (depending on the concrete shortage)
  • Tolerancing rock and backfilling curbs 11-7 thru 11-11
  • Blacktop would be around 11-17-22